26 Maria Place

26 Maria Place

Ponte Vedra Beach, FL 32082

 

Watch this video for details on the PREFER model and the 26 Maria Place property.


PREFER Loan Amount

Total Raise: $1,400,000

  • Down Payment: $1,035,000

  • Origination Fee: 2.75%

  • Closing Costs: $169,315

  • Construction Fee & Costs: $24,500

  • Wholesale Fee: $80,000

  • Carrying Cost (6-8 Months): $250,000

PREFER Secured Loan Interest: $364,000

Cash on Cash Return: 26%

BECOME A LENDER ON A SIMILAR DEAL

Property Details

  • 4 Beds, 4 Baths, 4,979 Sq. Ft.

  • Waterfront on 0.78 Acre Lot

  • Exclusive Old Ponte Vedra Beach

  • Blocks from Atlantic Ocean

  • Pool + Three Outdoor Patios

Rehab Details

  • Full Demo in Kitchen & Oversized Luxury Appliances

  • All Bathrooms Remodeled

  • Interior & Exterior Paint

  • New Flooring, Windows and Sliders

Property Data

Buy Price: $3,800,000

  • Mortgage Amount: $3,564,500

  • Rehab Cost: $1,050,000

  • Estimated Completion: 6-8 Months

Estimated After Repair Value: $6.5-6.7M

Estimated to Market: July 2026

Estimated Payout: Fall 2026

The PREFER Model

  • High-End Luxury Fix & Flips

    • Operating only in coastal markets

    • Choosing properties that are not selling for their full value because they’re out of date and missing the key features & amenities luxury buyers are looking for.

  • Totally Passive

  • Short-Term Cash on Cash Returns

    • 6-8 Month Rehab Timeline

    • Returns Expected Within 12 Months

  • Fractional - $50,000 Minimum

  • Geographic Mobility

    • Lender doesn’t have to be local to the property.

  • Extensive Due Diligence

    • Several third-party appraisals and consultations with local real estate agents and professionals to ensure these deals will produce the expected returns.

Property Updates

07.18.25 Update

  • New plumbing valves installed

  • Tear out and landscaping in progress

  • Built-ins for the deck on the water

08.23.25 Update

  • Framing is complete

  • New outdoor pergola being constructed

  • New dock being installed

08.01.25 Update

  • New insulation going in

  • Adjusting framing for more privacy in master bedroom

  • Butler’s pantry underway

08.29.25 Update

  • Plumbing completed

  • Electrical completed

  • Awaiting inspection to move forward

09.19.25 Update

  • Custom cabinets underway

  • Marble and quartz ordered

  • All windows and sliders installed

09.05.25 Update

  • Plumbing & Electrical completed

  • Awaiting inspection to move forward

  • New windows and sliders being installed

  • New dormers completed

12.06.25 Update

  • Custom cabinets underway, prepping for install

  • New custom bar cabinetry underway

  • Prepping for appliance installation

  • Sheetrock complete

  • Exterior brickwork removed/replaced

  • Windows covered and prepping for exterior paint

10.24.25 Update

  • Plumbing valves installed

  • Electrical complete

11.08.25 Update

  • Custom cabinets underway

  • New custom bar cabinetry underway

  • Appliances en route

  • Drywall installed

  • Exterior brickwork being removed

11.01.25 Update

  • Custom cabinet maker on site this week

  • Final plumbing rough ends completed and floors closed

  • New custom bar cabinetry underway

  • Some lighting ordered

05.23.25 Update

  • HVAC, plumbing, electrical wrap up this week with roughs and inspections

  • Dormers in process

  • Drywall anticipated by June 2nd

06.06.25 Update

  • New dormers in progress.

  • Cabinet layout in progress.

  • Insulation and drywall are next.

  • Additional concrete necessary for additional new plumbing to the street due to old cast iron line.

05.30.25 Update

  • Plumbing almost complete

  • New windows & interior doors installed

  • Electrical is complete

  • HVAC in process

09.26.25 Update

  • Custom cabinets underway

  • Additional plumbing completed

  • Marble ordered for fabrication

  • Fireplace torn out and plans underway for custom bar

10.17.25 Update

  • Custom cabinets underway

  • Final plumbing rough ends completed

  • New custom bar cabinetry underway

  • Awaiting inspection

  • Drywall expected to begin next week

  • Appliance package ordered

  • Final sliders and windows installed

10.04.25 Update

  • Custom cabinets underway

  • Final plumbing installed for both kitchens

  • Dock completed

  • HVAC underway

  • Awaiting inspection

  • Drywall expected to begin next week

06.13.25 Update

  • Major drainage fix under-way

  • Framing corrections under-way

  • HVAC to follow framing corrections

07.07.25 Update

  • Inspections passed last week

  • Plumbing top-out in progress

  • Running additional gas lines

  • Backfilling on trenches

06.20.25 Update

  • Major drainage fix and framing corrections are under-way

  • HVAC to follow

03.14.25 Update

  • Framing is done

  • Rough MEP’s starting next week

02.28.25 Update

  • Demo in process

  • Plans & engineering in process

03.07.25 Update

  • Demo is done

  • Framing starting today

  • Rough MEP’s next week

  • Windows have been ordered

  • Go-To-Market Expected in June

04.04.25 Update

  • MEPs in next 10 days

  • Plumbing, Electrical, and HVAC soon

  • Expected Construction Completion in July

03.21.25 Update

  • Demo & framing are done

  • Rough MEP’s starting

  • Plans finalized for engineering permit

03.28.25 Update

  • Framing finished

  • Plumbing, Electrical, and HVAC are next

05.16.25 Update

  • Electric & plumbing in progress

  • Re-framing is complete

  • Gas & water lines being installed

04.18.25 Update

  • Concrete cutting for plumbing

05.09.25 Update

  • Framing is complete

  • Trenches cut for new plumbing

  • Electric & plumbing have started

11.15.25 Update

  • Custom cabinets underway

  • New custom bar cabinetry underway

  • Insulation near completion

  • Drywall installation has begun

  • Exterior brickwork being removed

11.22.25 Update

  • Custom cabinets underway off-site

  • Drywall/sheetrock underway

  • Exterior brickwork complete

  • Insulation complete

  • Dormers caulked & trimmed for exterior painting

01.03.26 Update

  • New custom bar cabinetry underway

  • Appliances ordered & prepped for installation

  • Sheetrock complete

  • Interior painting underway

  • Floor being prepped for tile

12.13.25 Update

  • Custom cabinets underway, prepping for install

  • New custom bar cabinetry underway

  • Prepping for appliance installation

  • Exterior primed for painting

01.31.26 Update

  • New custom bar cabinetry underway

  • Custom cabinets underway and prepping for installation

  • All bathroom floor & shower tile complete

  • Interior painting underway

  • Great room & master bed fireplaces installed

01.17.26 Update

  • New custom bar cabinetry underway

  • Primary bathroom floor and shower tile complete

  • Great room and master fireplaces complete

  • Interior painting underway

  • Coffered ceiling in dining room complete

02.14.26 Update

  • New custom bar cabinetry underway

  • Custom cabinets underway and prepping for installation

  • All bathroom floor & shower tile complete

  • Interior painting underway

  • Fireplace stone & mantles selected

03.07.26 Update

  • New custom bar cabinetry underway

  • Custom cabinets underway and prepping for installation

  • All bathroom floor & shower tile complete

  • Interior painting underway

  • Fireplace stone & mantles selected

04.03.26 Update

  • Doors Installed

    Custom Kitchen cabinet installation has started

    Flooring installation underway

    Bathroom tile complete 

    Shower tile complete 

    Fixtures in showers complete

    Exterior paint complete

    Bathtubs and toilets installed 

    Interior paint complete

03.20.26 Update

  • Doors Installed

  • Custom Kitchen cabinets to begin being installed 

  • Flooring to ready to be installed

  • Bathroom tile complete 

  • Shower tile complete 

  • Fixtures in showers complete

  • Exterior paint complete

  • Bathtubs and toilets installed 

  • Interior paint complete

06.26.26 Update

  • Left to complete: 

    • Pool Complete

    • Landscaping Underway

    • Hardscaping Underway

    • Appliance Installation Complete

    • Glass on front door Complete

    • Tile on Fireplaces

04.17.26 Update

  • Interior Painitng complete

    Electrical trim 80% complete

    HVAC Complete

    Plumbing trim 80% complete

    Wood floors/tile complete

    Doors are set, trimmed and 50% of hardware installed

    Window trim and base complete

    Stair treads and risers are underway

    Herringbone dining room floor to begin

    Cabinets and vanities 80% complete

    Both fireplaces installed

    Appliances are on site

    Garage doors installed

    Landscaping prep/demo started today

    Gutters are installed

    Pool starting  Monday

    Demo on Driveway to begin

05.01.26 Update

  • Interior painting complete and being bumped out

  • Electrical trim 80% complete – 95%

  • HVAC has been running and is trimmed out

  • Plumbing is 60% trimmed out

  • Wood Floors and tile are 99%

  • Doors are set, trimmed and 50% of the hardware installed

  • Window trim and base are complete

  • Stair treads and risers  are complete - herringbone dining room 50%

  • Cabinets and Vanities 80% complete

  • Both Fireplaces are installed

  • Appliances are on site

  • Garage doors are installed

  • Exterior painting is complete

  • Landscaping started demo/prep today

  • Gutters are installed

  • Pool is in motion

  • Attic access installed

  • Shoe molding installed

  • Front door delivered and installed – waiting on side lights

  • Shower doors are scheduled for installation Monday

  • Counters are scheduled for Monday

  • Plumbers are schedule right behind them and the preside for the appliances

05.15.26 Update

  • Left to complete: 

    • Door and cabinet hardware

    • Landscaping

    • Appliance Installation

    • Glass on front door

    • Tile on Fireplaces

    • Pool

07.11.26 Update

  • PROJECT COMPLETE

    • Professional photos will be taken next week

    • Listing will go LIVE this month

    • List Price $7.295M

07.24.26 Update

  • PROJECT COMPLETE

    • Professional photos taken 7/23

    • Listing will go LIVE 7/24, 7/25